Cupertino Civic Center

Cupertino Civic Center

Cupertino, CA

Completed in 2004, the Cupertino Civic Center has 18,600 square feet of brick and 6,400 square feet of concrete block masonry. The Civic Center used 4" Norman brick veneer with 3 colors of brick. A Burke Fleming System over steel studs was selected to meet the expectation for quality in design. The selection of the building material was as important as the architectural style.

The brick veneer and the CMU added visual richness to the building as well as aesthetic value and structural strength.

Cupertino Civic Center
Cupertino Civic Center
Cupertino Civic Center
Cupertino Civic Center
Cupertino Civic Center
Cupertino Civic Center
(click on photos to enlarge)

Owner

City of Cupertino
Cupertino, CA

Architect

SMWM Architecture
San Francisco, CA

Structural Engineer

Forell/Elsesser Engineers, Inc.
San Francisco, CA

General Contractor

Swinerton Builders
Santa Clara, CA

Mason Contractor

John Jackson Masonry
Sacramento, CA

Masonry Material Suppliers

Interstate Brick Co.
Basalite Block Co.

Cost of Masonry

$825,000

John Jackson Masonry 5691 Power Inn Road, Suite B Sacramento, CA 95824 P: 916-381-8021 F: 916-381-1202